|
YAP YEW CHEONG
& ANOR V. DIRGA NIAGA (SELANGOR) SDN BHD
HIGH COURT MALAYA, KUALA LUMPUR
[CIVIL SUIT NO: S6-22-533-2004]
ABDUL MALIK ISHAK J
12 AUGUST 2005
JUDGEMENT
Abdul Malik Ishak J:
Introduction
This is an appeal by the defendant in encl. 13 against the learned senior
assistant registrar's ("SAR") decision in favour of the plaintiffs' summary
application pursuant to O. 14 of the Rules of the High Court 1980 ("RHC").
Factually speaking, the appeal centred on three agreements entered into
between the plaintiffs and the defendant. These agreements are not the
standard sale and purchase agreements under the Housing Developers (Control
and Licensing) Regulations 1989 made under the Housing Developers (Control
and Licensing) Act 1966. In fact, these three agreements are "set-off"
agreements entered into for purposes of setting-off all the debts due from
Europlus Corporation Sdn Bhd to WCT Engineering Bhd. The defendant is an
associated or a subsidiary to Europlus Corporation Sdn Bhd while the
plaintiffs are the directors of WCT Engineering Bhd. These three agreements
are drafted by the plaintiffs' solicitors and they are, incidentally, the
solicitors representing the plaintiffs in this action.
It was a term in these agreements that the defendant shall within six (6)
months from 23 January 1998 (the date of the sale and purchase agreements)
redeem the said parcels (which will be referred to shortly) and deliver to
the plaintiffs a letter of disclaimer failing which the defendant shall pay
to the plaintiffs as purchasers 12% interest on daily rests on the purchase
price from the expiry of the six (6) months to the date of actual redemption
(hereinafter referred to as the "LAD").
The plaintiffs purchased parcel no: F 10 at RM371,200 with LAD at
RM146,323.98, parcel no: F 41 at RM328,900 with LAD at RM129,649.67 and
parcel no: F 42 at RM328,900 with LAD at RM129,649.67. The total LAD came up
to RM405,623.32. It was quite substantial.
It is undisputed that the letter of disclaimer was dated 5 November 2001 and
calculation-wise the delay was from 22 July 1998 to 5 November 2001 which
came up to 1199 days for the three units.
Arguments Advanced By The Defendant
It may be summarised in the following manner:
(a) that the plaintiffs are enforcing a penalty clause which is invalid in
the Malaysian context and in Malaysia generally by virtue of and pursuant to
s. 75 of the Contracts Act 1950; and
(b) that the plaintiffs are claiming compounding interest by imposing 8%
upon 12% which is said to be contrary to s. 11 of the Civil Law Act 1956.
In fact, these are the two salient issues for the court to deliberate upon.
The determination of these two issues would dispose off the defendant's
appeal in encl. 13, once and for all.
I shall now proceed to examine these two issues summarily.
The First Issue
The clause which is said to be a penalty clause is found in the sale and
purchase agreement between the defendant and the plaintiffs dated 23 January
1998 as seen in exh. "YYC1" to the first plaintiff's affidavit affirmed on 2
June 2004 as reflected in encl. 5 (hereinafter referred to as the "said
clause") and I must be forgiven for reproducing the said clause:
2. Redemption of the said Parcel
(1) The vendor (referring to the defendant) shall within six (6) months from
the date hereof redeem the said parcel from the bridging financier and
deliver to the purchaser(s) (referring to the plaintiffs) a letter of
disclaimer (hereinafter called the "letter of disclaimer") from the bridging
financier disclaiming all rights title and interest to the said parcel and
undertaking to exclude the same from any foreclosure proceedings, if any
action of such a nature is instituted against the vendor (referring to the
defendant) on the said lands.
(2) If upon the expiry of the said six (6) months the vendor (referring to
the defendant) shall fail to redeem the said parcel from the bridging
financier rendering the said parcel free from all encumbrances the vendor
(referring to the defendant) shall pay to the purchaser(s) (referring to the
plaintiffs) interests at twelve per centum (12%) per annum on daily rests on
the purchase price from the date of expiry of the said six (6) months to the
date of actual redemption or it shall cause Europlus to pay to the
purchaser(s) (referring to the plaintiffs) the said interests.
Can the said clause be considered to be a penalty clause? Can we construe
the said clause to be a liquidated damages clause? These are pertinent
questions to pose in adjudicating the defendant's appeal in encl. 13. The
essential difference between penalties and liquidated damages has been
lucidly explained in Dunlop Pneumatic Tyre Co., Ltd. v. New Garage and Motor
Co., Ltd.[1914-15] All ER Rep. 739, a decision of the House of Lords with a
coram of Lord Dunedin, Lord Atkinson, Lord Parker and Lord Parmoor. There,
Lord Dunedin has this to say (see p. 741 to p. 742 of the report):
We had the benefit of a full and satisfactory argument, and a citation of
the very numerous cases which have been decided on this branch of the law.
The matter has been handled, and at a recent date, in the courts of highest
resort. I particularly refer to Clydebank Engineering Co. v. Yzquierdo y
Castaneda (Don Jose Ramos)[1905] AC 6; 74 LJPC 1; 91 LT 666; 21 TLR 58, HL;
17 Digest (Repl.) 149, 489, in your Lordships' House, and Public Works Comr.
v. Hills[1906] AC 368; 75 LJPC 69; 94 LT 833, PC; 17 Digest (Repl.) 149, 490
and Webster v. Bosanquet[1912] AC 394; 81 LJPC 205; 106 LT 357; 28 TLR 271,
PC; 17 Digest (Repl.) 156, 532, in the Privy Council. In all these cases
many of the previous authorities were considered. In view of that fact, and
of the number of the authorities available, I do not think it advisable to
attempt any detailed review of the various cases, but I shall content myself
with stating succinctly the various propositions which I think are deducible
from the decisions which rank as authoritative:
(i) Though the parties to a contract who use the words penalty or liquidated
damages may prima faciebe supposed to mean what they say, yet the expression
used is not conclusive. The court must find out whether the payment
stipulated is in truth a penalty or liquidated damages. This doctrine may be
said to be found passim in nearly every case. (ii) The essence of a penalty
is a payment of money stipulated as in terrorem of the offending party; the
essence of liquidated damages is a genuine covenanted pre-estimate of
damage: Clydebank Engineering Company v. Yzquierdo y Castaneda (Don Jose
Ramos)[1905] AC 6; 74 LJPC 1; 91 LT 666; 21 TLR 58, HL; 17 Digest (Repl.)
149, 489. (iii) The question whether a sum stipulated is penalty or
liquidated damages is a question of construction to be decided upon the
terms and inherent circumstances of each particular contract, judged of as
at the time of the making of the contract, not as at the time of the breach:
Public Works Comr. v. Hills[1906] AC 368; 75 LJPC 69; 94 LT 833, PC; 17
Digest (Repl.) 149, 490 and Webster v. Bosanquet[1912] AC 394; 81 LJPC 205;
106 LT 357; 28 TLR 271, PC; 17 Digest (Repl.) 156, 532. (iv) To assist this
task of construction various tests have been suggested, which, if applicable
to the case under consideration, may prove helpful or even conclusive. Such
are: (a) It will be held to be a penalty if the sum stipulated for is
extravagant and unconscionable in amount in comparison with the greatest
loss which could conceivable be proved to have followed from the breach -
illustration given by Lord Halsbury, LC, in the Clydebank Engineering
Company v. Yzquierdo y Castaneda (Don Jose Ramos)[1905] AC 6; 74 LJPC 1; 91
LT 666; 21 TLR 58, HL; 17 Digest (Repl.) 149, 489. (b) It will be held to be
a penalty if the breach consists only in not paying a sum of money, and the
sum stipulated is a sum greater than the sum which ought to have been paid:
Kemble v. Farren[1829] 6 Bing. 141; 3 Moo. & P. 425; 7 LJO SCP 258; 130 ER
1234; 17 Digest (Repl.) 157, 546. This, though one of the most ancient
instances, is truly a corollary to the last test. Whether it had its
historical origin in the doctrine of the common law that, when A. promised
to pay B. a sum of money on a certain day and did not do so, B. could only
recover the sum with, in certain cases, interest, but could never recover
further damages for non-timeous payment, or whether it was a survival of the
time when equity reformed unconscionable bargains merely because they were
unconscionable - a subject which much exercised Jessel, MR, in Wallis v.
Smith[1882] 21 Ch. D. 243; 52 LJ Ch. 145; 47 LT 389; 31 WR 214, CA; 17
Digest (Repl.) 77, 14 - is probably more interesting than material. (c)
There is a presumption (but no more) that it is a penalty when
a single lump sum is made payable by way of compensation, on the occurrence
of one or more or all of several events, some of which may occasion serious
and others but trifling damages:
per Lord Watson in Lord Elphinstone v. Monkland Iron and Coal Co.[1886] 11
App. Cas. 332; 35 WR 17, H.L.; 17 Digest (Repl.) 158, 555 (11 App. Cas. at
p. 342). On the other hand: (d) It is no obstacle to the sum stipulated
being a genuine pre-estimate of damage that the consequences of the breach
are such as to make precise pre-estimation almost an impossibility. On the
contrary, that is just the situation when it is probable that pre-estimated
damage was the true bargain between the parties:Clydebank Engineering
Company v. Yzquierdo y Castaneda (Don Jose Ramos)[1905] AC 6; 74 LJPC 1; 91
LT 666; 21 TLR 58, HL; 17 Digest (Repl.) 149, 489 per Lord Halsbury; Webster
v. Bosanquet[1912] AC 394; 81 LJPC 205; 106 LT 357; 28 TLR 271, PC; 17
Digest (Repl.) 156, 532 per Lord Mersey.
That is certainly an interesting exposition of the law. In Malaysia, it
seems that there is no difference between a penalty and liquidated damages
and, accordingly, it would attract the provisions of s. 75 of the Contracts
Act 1950. The position has been lucidly stated by Thomson J in SS Maniam v.
The State Of Perak[1956] 1 LNS 112; [1957] MLJ 75 in this way (see p. 76 of
the report):
In the first place, in this country there is no difference between penalty
and liquidated damages. Section 75 of the Contract Ordinance which is the
same as section 74 of the Indian Contract Act reads as follows:
When a contract has been broken, if a sum is named in the contract as the
amount to be paid in case of such breach, or if the contract contains any
other stipulation by way of penalty, the party complaining of the breach is
entitled, whether or not actual damage or loss is proved to have been caused
thereby, to receive from the party who has broken the contract reasonable
compensation not exceeding the amount so named or, as the case may be, the
penalty stipulated for.
As is said in Pollock and Mulla on the Indian Contract Act(7th Edition, page
410) 'This section boldly cuts the most troublesome knot in the Common Law
doctrine of damages.' In brief, in our law in every case if a sum is named
in a contract as the amount to be paid in case of breach it is to be treated
as a penalty. See Bhai Panna Singh v. Bhai Arjun SinghAIR [1929] PC 179.
To me, the distinction between liquidated damages and penalty is of no
significance. It is of no legal importance simply because it is the duty of
the court in either case to determine the quantum of what is the reasonable
compensation to be handed out. It is wrong to say that a penalty clause is
invalid by virtue of s. 75 of the Contracts Act 1950. Both the liquidated
damages and penalties exist side by side. In liquidated damages, there will
be a genuine pre-estimate of the loss that will be caused to one party in a
situation where the contract is broken by the other. It is this liquidated
damages that would be recoverable and it requires no proof of actual damage
(per Cotton LJ in Wallis v. Smith[1882] 21 Ch D 243 at 267). Whereas it is
said that a penalty clause constitutes a threat held against the opposite
party in terrorem; more in the nature of a security extended to the promisee
to the effect that the contract will be performed. But Lord Radcliffe in
Bridge v. Campbell Discount Co Ltd[1962] AC 600 at 622, [1962] 1 All ER 385
at 395 has been very vocal and his Lordship has expressed his scepticism
that a penalty is based on a threat in terrorem of the opposite party. Be
that as it may, a penalty clause is always subject to the equitable
jurisdiction of the court. So, the courts of equity would always ensure that
a promisee is sufficiently compensated for his actual loss. However, there
may be cases where the agreed sum may be less than the damage actually
suffered yet the promisee may recover his actual loss (Public Works Comr v.
Hills[1906] AC 368 at 375; Wall v. Rederiaktiebolaget Luggude[1915] 3 KB 66;
and Watt, Watts & Co Ltd v. Mitsui & Co Ltd[1917] AC 227). In Bulsing Ltd v.
Joon Seng & Co[1971] 1 LNS 13; [1972] 2 MLJ 43, Chua J was of the view that,
in a penalty clause situation, the promisee has an option whether to sue
under the penalty clause or to sue for damages and recover damages in full.
At the end of the day, it is purely a matter of construction for me to
decide by looking upon and perusing the terms and inherent circumstances of
each particular case viewed objectively as at the time of entering into the
contract and not at the time of the breach thereof. This is the approach
recommended by other Judges before me in the following cases:
(1) Dunlop Pneumatic Tyre Co., Ltd. v. New Garage and Motor Co., Ltd.
(supra);
(2) Lombank Ltd v. Excell[1963] 3 All ER 486; and
(3) Phoenix Heights Estate (Pte) Ltd v. Lee Kay Guan[1982] CLJ 44 (Rep) ;
[1982] 2 MLJ 86.
Lopes J puts it rather well in the case of Law v. Redditch Local Board[1982]
1 QB 127 at 132:
The distinction between penalties and liquidated damages depends on the
intention of the parties to be gathered from the whole of the contract. If
the intention is to secure performance of the contract by the imposition of
a fine or penalty, then the sum specified is a penalty; but if, on the other
hand, the intention is to assess the damages for breach of the contract, it
is liquidated damages.
And the onus of showing that the specified sum is a penalty lies upon the
shoulders of the party who is being sued for its recovery (Robophone
Facilities Ltd v. Blank[1966] 1 WLR 1428 at 1447). According to Lord Dunedin
in Dunlop Pneumatic Tyre Co., Ltd. v. New Garage and Motor Co., (supra)notwithstanding
the fact that the parties may have used expressions like "penalty" or
"liquidated damages" it is not conclusive and it is up to the court to
decide whether it is a penalty or liquidated damages.
I reiterate that it is wrong to say as was said by the defendant that a
penalty clause is invalid in Malaysia in the context of s. 75 of the
Contracts Act 1950. In Malaysia, the distinction between liquidated damages
and penalties has no significance. It has been put into oblivion by s. 75 of
the Contracts Act 1950 (Choo Yin Loo v. SK Visuvalingam Pillay[1930] 7 FMSLR
135; The Hua Khiow Steamship Co Ltd v. Chop Guan Hin[1930] 1 MC 175, 1 JLR
33; SS Maniam v. The State Of Perak (supra); Wearne Bros (M) Ltd v.
Jackson[1966] 2 MLJ 155; Linggi Plantations Ltd v. Jagatheesan[1971] 1 LNS
66; [1972] 1 MLJ 89; and Wee Wood Industries Sdn Bhd v. Guannex Leasing Sdn
Bhd[1990] 2 CLJ 1060; [1990] 3 CLJ (Rep) 355). Section 75 of the Contracts
Act 1950 enacts as follows:
Compensation for breach of contract where penalty stipulated for.
75. When a contract has been broken, if a sum is named in the contract as
the amount to be paid in case of such breach, or if the contract contains
any other stipulation by way of penalty, the party complaining of the breach
is entitled, whether or not actual damage or loss is proved to have been
caused thereby, to receive from the party who has broken the contract
reasonable compensation not exceeding the amount so named or, as the case
may be, the penalty stipulated for.
Explanation - A stipulation for increased interest from the date of default
may be a stipulation by way of penalty.
Exception - When any person enters into any bail-bond, recognizance, or
other instrument of the same nature, or, under the provisions of any law, or
under the orders of the Federal Government or the Government of any State,
gives any bond for the performance of any public duty or act in which the
public are interested, he shall be liable, upon breach of the condition of
any such instrument, to pay the whole sum mentioned therein.
Explanation - A person who enters into a contract with Government does not
necessarily thereby undertake any public duty, or promise to do an act in
which the public are interested.
ILLUSTRATIONS
(a) A contracts with B to pay B $1,000, if he fails to pay B $500 on a given
day. A fails to pay B $500 on that day, B is entitled to recover from A such
compensation, not exceeding $1,000, as the court considers reasonable.
(b) A contracts with B that, if A practices as a surgeon within Calcutta, he
will pay B $5,000. A practices as a surgeon in Calcutta. B is entitled to
such compensation, not exceeding $5,000, as the court considers reasonable.
(c) A gives a recognizance binding him in a pena1ty of $500 to appear in
court on a certain day. He forfeits his recognizance. He is liable to pay
the whole penalty.
(d) A gives B a bond for the repayment of $1,000 with interest at 12 per
cent. at the end of six months, with a stipulation that, in case of default,
interest shall be payable at the rate of 75 per cent. from the date of
default. This is a stipulation by way of penalty, and B is only entitled to
recover from A such compensation as the court considers reasonable.
(e) A who owes money to B, a moneylender, undertakes to repay him by
delivering to him 10 gantangs of grain on a certain date, and stipulates
that, in the event of his not delivering the stipulated amount by the
stipulated date, he shall be liable to deliver 20 gantangs. This is a
stipulation by way of penalty, and B is only entitled to reasonable
compensation in case of breach.
(f) A undertakes to repay B a loan of $1,000 by five equal monthly
instalments, with a stipulation that, in default of payment of any
instalment, the whole shall become due. This stipulation is not by way of
penalty, and the contract may be enforced according to its terms.
(g) A borrows $100 from B and gives him a bond for $200 payable by five
yearly instalments of $40, with a stipulation that, in default of payment of
any instalment, the whole shall become due. This is a stipulation by way of
penalty.
Some critics say that in order to recover compensation in the course of the
trial, the plaintiff must prove the actual damage suffered. But this would
run counter to the phrase "whether or not actual damage or loss is proved to
have been caused thereby" that appears in s. 75 of the Contracts Act 1950.
What constitutes "reasonable compensation" within the meaning of s. 75 of
the Contracts Act 1950 must necessarily be the actual damage suffered by the
plaintiff. The Federal Court in the case ofSelva Kumar a/l Murugiah v.
Thiagarajah a/l Retnasamy[1995] 2 CLJ 374 speaking through Peh Swee Chin FCJ
who after going through some Indian precedents held that proof of damage or
loss was necessary.
In short, the Selva Kumar's case requires an injured party to prove his
actual loss and it is depriving him of the very benefit a liquidated damages
clause was intended to confer viz, recovery without proof of actual loss.
According to Mr. Seah Ban Kiat, the learned counsel for the defendant, who
hails from the law firm of Messrs Yeap & Yong, that the Selva Kumar's case
bears grave implications for the construction industry since an injured
party must prove his actual loss for late completion notwithstanding the
liquidated damages clause. The Federal Court in Selva Kumarheld that:
(1) by reason of s. 75 of the Contracts Act 1950, a liquidated damages
clause is deemed to be penal and therefore invalid except as a ceiling for
recovery. Accordingly, the sum expressed as liquidated damages cannot, in
and of itself, be automatically recovered by the injured party;
(2) so much so that even if a contract has a liquidated damages clause, an
injured party must still prove his actual loss, for instance, an employer
must prove his actual loss for late completion;
(3) but, if it is very difficult for the injured party to prove his actual
loss because there is "no known measure of damages employable" for the
breach in question then his claim would not fail. Instead, s. 75 of the
Contracts Act 1950 would permit him to recover a "reasonable compensation"
which is "reasonable and fair according to the court's good sense and fair
play" capped at the value of the sum expressed as liquidated damages; and
(4) that the relevant words in s. 75 of the Contracts Act 1950 that permits
the injured party to obtain recovery despite being unable to prove his
actual loss are the words "whether or not actual damage or loss is proved to
have been caused thereby". These words are therefore to be narrowly
interpreted and should not be taken to mean that an injured party could
simply deduct the liquidated damages by using a liquidated damages clause
without having to prove his actual loss.
It is appropriate, at this juncture, to reproduce the speech of Peh Swee
Chin FCJ in Selva Kumar's case:
It would still be left to the good sense and fair play of the court to fix a
reasonable amount as compensation. Thus, it will mean that for lack of an
established measure of damages in any particular case, that case will be one
in which the court finds it difficult to ascertain the amount of actual loss
or damage. The court will not shirk its duty, however, when such actual loss
or damage is manifested from the evidence and it is not too remote, to find
a reasonable sum for the plaintiff.
Continuing in the case of Selva Kumar, Peh Swee Chin FCJ expressed his views
thus:
Thirdly, therefore, we hold that the precise attributes of such contracts in
which it is difficult for a court to assess damages for the actual damage or
loss, are cases where there is no known measure of damages employable, and
yet the evidence clearly shows some real loss inherently and such loss is
not too remote; then the court ought to award, not nominal damages, but
instead, substantial damages not exceeding the sum so named in the
contractual provision, a sum which is reasonable and fair according to the
court's good sense and fair play.
Fourthly, we hold that in any case where there is inherently any actual loss
or damage from the evidence or nature of the claim and damage for such
actual loss is not too remote and could be assessed by settled rules, any
failure to bring in further evidence or to prove damages for such actual
loss or damage, will result in the refusal of the court to award such
damages, despite the words in question.
The learned counsel for both the plaintiffs by the name of Miss Jashirita
binti Mohd Bashir from Messrs Yip & Co submits with vigour and vitality that
the facts in Selva Kumarare different from the facts of the present case.
According to her, in Selva Kumar, the clause pertaining to the liquidated
ascertained damages was unreasonable because the said clause stated that in
the event the purchaser defaulted, all monies paid by the purchaser may be
forfeited by the vendor. There, according to her, the vendor sought to
forfeit all the monies paid by the purchaser which was 80% of the purchase
price. Therefore, according to her, surely the Federal Court in that case
was minded to find that s. 75 of the Contracts Act 1950 would not apply in
the strict sense of the word. She emphasised that the case of Selva Kumarwas
a case concerning the sale and purchase of a medical practice. And that the
Federal Court was of the opinion that the respondent would have proved the
actual loss or the damage that he has suffered, for example, the use of
medical equipments at the clinic. But, unfortunately, according to her, the
respondent has failed to do so and, consequently, the Federal Court was
unable to quantify any award of damages to him.
I am attracted to the case of Sakinas Sdn Bhd v. Siew Yik Hau & Anor[2002] 3
CLJ 275, a decision of Abdul Aziz Mohamed J (now JCA). That case would be
more relevant and appropriate in adjudicating the present appeal at hand. It
was a construction related case and it involved purchasers of a condominium
apartment. The agreement was in accordance with reg. 11 of the Housing
Developers (Control and Licensing) Regulations 1989 read with Schedule "H"
thereto and they were made under the Housing Developers (Control and
Licensing) Act 1966. It was in the nature of a mandatory contract for the
sale and purchase of the condominium apartment. The developers defaulted and
failed to hand over vacant possession of the condominium apartment in time
and there was also a corresponding failure to complete the common facilities
in time. In both situations, the delay came up to 3
|