Maintenance fee: Tribunal rules in 
      favour of developer 
       
      dailyexpress.com.my
      28/4/2005
      Kota Kinabalu: In a rare outcome, the Consumer Claims 
      Tribunal on Tuesday decided in favour of the respondent, a housing 
      developer, in respect of unpaid maintenance fee on the part of the 
      claimant.  
       
      Tribunal President, Hussain Mohamed Dewa, said he would not want to set a 
      precedence whereby apartment occupants will think it's okay to refuse 
      paying maintenance fee on the excuse that the developer, through its 
      Management Corporation (MC), had failed to "look after their interest".
       
       
      Ordering the claimant, a Selesa Court resident, to instead pay the 
      respondent, Globally Group Sdn Bhd, his dues amounting to RM1,714.60, 
      Hussain who has served as a Magistrate, a Martial Court judge and a 
      Syariah Court judge, said it would have far reaching consequences if he 
      didn't make the award in favour of the respondent.  
       
      "You have to pay up your dues," he said, referring to the case in which 
      the resident filed a claim against the developer in a bid to compel the 
      latter to allow them to receive water direct from the Water Department's 
      main pipe located outside the compound.  
       
      The MC is presently supplying the water to the residents pumped from the 
      main pipe to a central tank. The management also handles the issuance of 
      the water bill.  
       
      The claimant had pointed to the failure of the MC to see to the immediate 
      rectification of the fault which lay with the wiring, causing the water 
      pump to cease functioning at 10pm on Jan. 15, this year. The residents had 
      to go without water for more than 24 hours.  
       
      Hussain, during the tribunal session, also explained to the claimant that 
      getting water direct from the authority was out of the question in the 
      case where the strata title has not been issued. Even the delay in the 
      issuance of the title cannot be held against the developer. So in the 
      event, the developer is responsible for managing the building through its 
      MC, he said.  
       
      He again asserted that payment of the maintenance fee must be made.
      "You cannot on your part not pay maintenance and want to claim for all the 
      amenities and the services. Nothing is free nowadays. It's just like you 
      have to pay income tax. What do you expect if you don't pay?"  
       
      Hussain said he is aware of the existence of the MC and the 'maintenance 
      fee' condition, which originated from the Ministry of Housing and Local 
      Government as he had served there for four years.  
       
      Citing a situation, he said, in Kuala Lumpur, if the occupants are not 
      satisfied with the arrangement, they can always report to the Exco of the 
      Ministry and their officers could come and advise the two parties during 
      their meetings.  
       
      "In this case, the fault was the work of rodents and not the respondent, 
      who was not able to get a mechanic that instant as the breakdown occurred 
      on a weekend.  
       
      "Unlike in KL, the MC would without hesitation cut off the water supply if 
      you don't pay up. That is wrong, of course," he added.  
       
      The respondent had actually counter-claimed for RM1,889.60 in back-dated 
      maintenance fee owned by the claimant, which the latter acknowledged at 
      the tribunal. Meanwhile, the tribunal struck off a claim by Mohamed Faisal 
      Mohd Noor after he failed to turn up for his case against Kenwood AV 
      Centre. It is learnt he is presently overseas. Faisal bought a CD player 
      for RM550 on April 17, 2004. It malfunctioned twice and he brought it to 
      the shop for repair.  
       
      He was surprised when asked to pay RM300 as the product was still under 
      warranty. He said he felt cheated and hence filed the claim to the 
      tribunal. 
       
       
      Hussain stressed he had to dismiss the case although Faisal had through 
      the tribunal's office requested for an adjournment. "But he did not give 
      us any date. We cannot leave this file hanging. Anyway, he can file again 
      later but he has to make himself available to come to the tribunal.  
       
      On the readiness of the respondent who was present, to negotiate, he 
      explained, even if there was an offer, it was still subject to acceptance 
      by the claimant.  |