     Home buyer in a spot  
    The Star 21/10/2005 
     
    KAVITHA’s dream house in Batu Caves is completed, but she’s still waiting 
    for the keys. 
     
    She wants to know what is delaying Sunway Mas Sdn Bhd from handing over the 
    keys. 
     
    “The project was completed in June, and we were promised that the keys would 
    be given to us in August. We have yet to receive them,” she says, adding 
    that she bought the house in June 2003. 
     
    The delay has put KAVITHA in a spot as she had sold the house she is 
    presently staying in because she could not afford to settle two housing 
    loans. 
     
    She claims that she had contacted the project manager many times, and was 
    told that the company was still waiting for the approval from Syarikat 
    Bekalan Air Selangor (Syabas) before issuing the the Certificate of Fitness 
    (CF). 
     
    “How long does it take to approve this?” she asks. 
     
    * A Sunway Mas Sdn Bhd spokesman says that except for Syabas, they have 
    received all the approvals for the CF. 
     
    He says that, as the developer, they have complied with all the requirement 
    set by Syabas. 
     
    “We have also asked for temporary water supply but there was no reply from 
    them,” he says, adding that the developer is also affected by the delay. 
     
    Syabas Corporate Affairs senior manager Abdul Halem Mat Som explains that 
    the delay is to allow them to study the technical aspects of the area. 
     
    “Nevertheless, on Oct 14, we wrote to the developer that we would approve 
    the temporary water supply application for the area provided that they 
    comply with the conditions and requirements imposed,” he says.  |