CHINAYA GANGGAYA V. SENTUL RAYA SDN BHD
HIGH COURT MALAYA, KUALA LUMPUR
[ORIGINATING SUMMONS NO: S3-24-599-2005]
HISHAMUDIN MOHD YUNUS J
18 DECEMBER 2007
JUDGMENT
Hishamudin Mohd Yunus J:
[1] By this originating summons action, the
plaintiff, who is a purchaser of an apartment (condominium unit) in a
condominium in Kuala Lumpur known as Sang Suria Condominium, claims against
the defendant company, a property developer from whom he had purchased the
condominium unit for, inter alia:
(a) a declaration that the defendant do pay to the
plaintiff liquidated damages (LAD) in the sum of RM165,962.89 pursuant to
cl. 22(2) of the sale and purchase agreement dated 23 September 1995; and
(b) a declaration that the defendant do pay to the
plaintiff liquidated damages (LAD) in the sum of RM33,191.92 pursuant to
cl. 24(2) of the sale and purchase agreement dated 23 September 1995.
[2] I have granted the order prayed for by the
plaintiff in the prayers in the originating summons.
[3] The facts of the present case, in particular,
on the issue of delay on the part of the defendant in handing over
possession of the condominium unit and completion of the common facilities,
are not disputed.
[4] The sale and purchase agreement was entered
into between the plaintiff and the defendant on 23 September 1995. The time
stipulated by the sale and purchase agreement for the delivery of vacant
possession of the condominium unit and for the completion of the common
facilities was 36 months from the date of the signing of the agreement.
[5] The defendant, however, failed to deliver
vacant possession of the condominium unit and to complete the common
facilities within the stipulated time. Delivery of vacant possession of the
condominium unit and completion of the common facilities were only performed
long after the due date, on 14 October 2002.
[6] The plaintiff claims for LAD from the
defendant because of the delay. But the defendant refuses to acknowledge
that the plaintiff is entitled to LAD, invoking s. 56(3) of the Contracts
Act 1950 and the doctrine of frustration.
[7] The defendant's opposition to the plaintiff's
claim raises two questions of law, namely:
(a) whether s. 56(3) of the Contracts Act 1950 applies,
and if so, whether this provision of the
Contracts Act precludes the plaintiff from claiming LAD; or,
alternatively,
(b) whether there was a frustration of the sale and
purchase agreement.
[8] At the outset, let it be pointed out that, in
the present case, the sale and purchase agreement entered into between the
plaintiff and the defendant is not an ordinary contract. It is not an
ordinary contract in the sense that the parties, when they drew up the terms
of the sale and purchase agreement, were not free to insert whatever terms
they considered fit into the contract. For most of the terms of the
contract, the parties had to incorporate into the sale and purchase
agreement the terms as prescribed by
reg. 11 and Schedule H of the Housing Developers (Control and Licensing)
Regulations 1989 (the "Housing Developers Regulations"). Only in respect of
certain terms, were parties free to agree and to have them incorporated in
the agreement; for example, terms pertaining to the price, the size of the
condominium unit and the quality of the material and finishing.
[9] The said reg. 11 of the Housing Developers
Regulations stipulates as follows:
11. Contract of sale.
(1) Every contract of sale for the sale and purchase
of a housing accommodation together with the subdivisional portion of
land appurtenant thereto shall be in the form prescribed in Schedule G
and where the contract of sale is for the sale and purchase of a housing
accommodation in a subdivided building, it shall be in the form
prescribed in Schedule H.
[10] The Housing Developers Regulations is a
subsidiary legislation made by the Minister of Housing and Local Government
in the exercise of his powers pursuant to s. 24 of the Housing Developers
(Control and Licensing) Act 1966 (the "Housing Developers Act").
[11]Section 24 of the Housing Developers Act
provides as follows:
24. Powers to make regulations.
(1) Subject to this section, the Minister may make
regulations for the purpose of carrying into effect the provisions of this
Act.
(2) In particular and without prejudice to the
generality of the foregoing power, the regulations may:
(b) prescribe the form or forms of contracts which
shall be used by a licensed housing developer, his agent, nominee or
purchaser both as a condition of the grant of a licence under this Act
or otherwise.
[12] Among the prescribed terms incorporated in
the sale and purchase agreement between the plaintiff and the defendant are
the following:
Clause 7. Time essence of contract.
Time shall be the essence of the contract in relation
to all provisions of this Agreement.
Clause 22. Time for handing over of vacant possession.
(1) Vacant possession of the said Parcel to which
water and electricity supply are ready for connection shall be handed
over to the Purchaser within thirty six (36) calendar months from the
date of this Agreement.
(2) If the Vendor fails to hand over vacant
possession of the said parcel, to which water and electricity supply are
ready for connection to the said Parcel, in time, the Vendor shall pay
immediately to the Purchaser liquidated damages to be calculated from
day to day at the rate of ten percentum (10%) per annum of the purchase
price.
Clause 24. Completion of common facilities.
(1) The common facilities serving the said housing
development shall be completed by the Vendor within thirty six (36)
calendar months from the date of this Agreement.
(2) If the Vendor fails to complete the common
facilities in time the Vendor shall pay immediately to the Purchaser
liquidated damages to be calculated from day to day at the rate of ten
percentum (10%) per annum of the last twenty per centum (20%) of the
purchase price.
[13] The wordings in cl. 7, cl. 22(1) and (2), cl.
24(1) and (2) above are exactly similar as the wordings of cl. 7, cl. 22(1)
and (2), and cl. 24(1) and (2) of the prescribed sale and purchase agreement
in Schedule H of the Housing Developers Regulations.
[14] It is to be observed that by the above cl. 7
of the standard sale and purchase agreement, entered into between the
parties, time was expressed to have been the essence.
[15] Since the sale and purchase agreement is not
an ordinary contract but is substantially governed by
reg. 11 and Schedule H of the Housing Developers Regulations, it follows
therefore that cls. 7, 22 and 24 of the sale and purchase agreement are not
mere terms of a contract: they are also statutory provisions since they are
actually provisions of Schedule H of the Housing Developers Regulations that
had been imposed by law upon the parties.
[16] In this regard, it is to be noted that s. 15
of the Interpretation Acts 1948 and 1967 prescribes:
15. Schedules.
Every schedule (together with any note or table annexed
thereto) to an Act or to any subsidiary legislation shall be construed and
have effect as part of the Act or subsidiary legislation.
[17] It is, as said above, argued by the learned
counsel for the defendant that the plaintiff is not entitled to LAD by
reason of s. 56(3) of the Contracts Act. Section 56 of the Contracts Act
provides:
56. Effect of failure to perform at fixed time, in
contract in which time is essential.
(1) When a party to a contract promises to do a
certain thing at or before a specified time, or certain things at or
before specified times, and fails to do any such thing at or before the
specified time, the contract, or so much of it as has not been
performed, becomes voidable at the option of the promisee, if the
intention of the parties was that time should be of the essence of the
contract.
Effect of failure when time is not essential.
(2) If it was the intention of the parties that time
should be of the essence of the contract, the contract does not become
voidable by the failure to do the thing at or before the specified time;
but the promisee is entitled to compensation from the promisor for any
loss occasioned to him by the failure.
Effect of acceptance of performance at time other than
that agreed upon.
(3) If, in case of a contract voidable on account of
the promisor's failure to perform his promise at the time agreed, the
promisee accepts performance of the promise at any time other than that
agreed, the promisee cannot claim compensation for any loss occasioned
by the non-performance of the promise at the time agreed, unless, at the
time of acceptance, he gives notice to the promisor of his intention to
do so.
[18] It is argued by the learned counsel for the
defendant that since time is the essence of the contract, therefore, by
reason of sub-s. (3) of s. 56, the plaintiff, as the innocent party, in
order to preserve his right to LAD under the sale and purchase agreement,
must give the defendant, the defaulting party, notice of his intention to
claim LAD for the delayed handing over of possession and completion of the
common facilities. Counsel refers to Sakinas Sdn Bhd v. Siew Yik Hau &
Anor [2002] 3 CLJ 275.
[19] It is contended by the defendant that the
plaintiff has failed to give the defendant such notice.
[20] With respect, I am unable to accept this
argument. In my judgment, I am in agreement with the learned counsel for the
plaintiff that the right of the plaintiffs to LAD is solely governed by cl.
22(2) and cl. 24(2) of the sale and purchase agreement entered into between
each of the plaintiffs and the defendant and the Housing Developers
Regulations (as well as the Housing Developers Act); and that s. 56(3) of
the Contracts Act has no relevance. The presence of the words "shall pay
immediately" in both the clauses is very significant in the interpretation
of both the clauses; and what the phrase means is that the right to be paid
LAD is automatic once there was a delay by the developer to hand over
possession or to complete the common facilities. The developer/defendant
must pay the LAD to the purchaser at once, without further ado, once there
was a delay. If the right to be paid is automatic, it follows then that
there was no obligation on the part of the purchasers/plaintiffs to give any
notice to the defendant. The phrase "shall pay immediately" would be
meaningless if the defendant's argument that notice was required were to be
accepted. I refer to my judgment in Tai Kim Yew v. Sentul Raya Sdn. Bhd.
[2004] 3 CLJ 310.
[21] The same view was expressed by Abdul Malik
Ishak J in Hariram a/l Jayaram v. Sentul Raya Sdn Bhd [2002] 4 CLJ
796; [2003] 1 MLJ 22. In this case cited, the facts are similar as the facts
of the present case. In fact, the plaintiff in that case was, like the
plaintiff in the present case, also a purchaser of the same condominium as
in the present case, that is, the Sang Suria Condominium in Kuala Lumpur;
and the defendant/developer in that case is the same defendant/developer as
in the present case: Sentul Raya Sdn Bhd. The learned judge in
Hariram, in his judgment, held (at p. 48):
... it must be emphasized that the word 'immediately'
that appears in both cll 22(2) and 24(2) of the sale and purchase
agreements which have been reproduced earlier would mean that the
purchasers have the right to claim the liquidated ascertained damages
without giving the requisite notices to the defendant under s. 56(3) of
the Contracts Act 1950.
[22] The proposition that this ought to be the
proper interpretation to be given to the phrase "shall pay immediately" can
be better appreciated if we were to consider the purpose behind the Housing
Developers Act, which is, to protect house buyers against the economically
powerful developers. It is to be recalled that, as earlier pointed out in
this judgment, the provisions of the sale and purchase agreement are special
provisions in that they are governed by the Housing Developers Act. In
SEA Housing Corporation Sdn Bhd v. Lee Poh Choo [1982] CLJ 355; [1982]
CLJ (Rep) 305, Suffian LP delivering the judgment of the Federal Court said:
It is common knowledge that in recent years, especially
when the government started giving housing loans making it possible for
public servants to borrow money at 4% interest per annum to buy homes,
there was an upsurge in demand for housing, and that to protect home
buyers, most of whom are people of modest means, from rich and powerful
developers, Parliament found it necessary to regulate the sale of houses
and protect buyers by enacting the Act.
[23] In City Investment Sdn Bhd v. Koperasi
Serbaguna Cuepacs Tanggungan Bhd [1987] 1 LNS 62; [1988] 1 MLJ 69, the
Judicial Committee of the Privy Council held (at p. 71):
This argument makes nonsense of an Act which is clearly
designed to protect purchasers from developers, and those purchasers need
protection whether the sites of houses before or contemporaneously with or
after completion of the houses.
[24] The same sentiment has been echoed by the
courts in the following cases:
(a) Khau Daw Yau v. Kin Nam Realty Development Sdn
Bhd [1982] 1 LNS 81; [1983] 1 MLJ 335 (per VC George J (as he then
was) at p. 341);
(b) Kang Yoon Mook Xavier v. Insun Development Sdn
Bhd [1995] 2 CLJ 471; [1995] 2 MLJ 91 (per Abdul Malik Ishak J at p.
99);
(c) Energoproject (M) Holdings v. Public Prosecutor
[1998] 5 MLJ 401 (per KC Vohrah J (as he then was) at p. 405) and
(d) Hariram a/l Jayaram v. Sentul Raya Sdn Bhd
[2002] 4 CLJ 796; [2003] 1 MLJ 22 (per Abdul Malik Ishak J at p. 37).
[25] I wish to add that the interpretation that I
(as well as the learned judge in Hariram) adopt in the present case is in
accord with s. 17A of the Interpretation Acts 1948 and 1967 which prescribes
the following principle of interpretation. This provision says:
17A. Regard to be had to the purpose of Act.
In the interpretation of a provision of an Act, a
construction that would promote the purpose or object underlying the Act
(whether that purpose or object is expressly stated in Act or not) shall
be preferred to a construction that would not promote that purpose or
object.
[26] Therefore, to accept the defendant's argument
is to make nonsense of the purpose of the Housing Developers Act, besides
offending s. 17A of the Interpretation Acts.
[27] Assuming that I am wrong in my above view,
and that s. 56(3) of the Contracts Act does apply to the sale and purchase
agreements, I would, nevertheless, hold that on the facts of the present
case, s. 56(3) does not apply. I so hold because, by reason of the words:
If ... the promisee accepts performance of the promise
at any time other than that agreed,
appearing in sub-s. (3), for the obligation on the part
of the plaintiff to give notice of intention to claim LAD to the defendant
to arise, it must be shown that (and the burden to adduce such evidence is
on the defendant) when the contracts became voidable, the plaintiff has
indicated to the defendant that it was acceptable to him if the defendant
fulfilled its promise at some other time other than the agreed date (see
Sakinas Sdn Bhd v. Siew Yik Hau [2002] 3 CLJ 275). But no such evidence
was ever adduced by the defendant.
[28] Now, it is further argued by the defendant,
in the alternative, that by reason of:
(a) the "abnormal" delay in handing over possession;
and that
(b) such delay was due to its dire financial position
brought about by the 1997-1998 national economic crisis which was beyond
its control, there was a frustration of the contract. The learned counsel
for the defendant cites the Indian Supreme Court case of Satyabrata
Ghose v. Mugneeram Bangur & Co [1954] AIR SC 44, and also the case of
Kung Swee Heng & Anor v. Pritam Kaur [1948] 1 LNS 23; [1948] 14 MLJ
170.
[29] In my judgment, this argument is also without
merit. The common law doctrine of frustration is codified in our law in the
form of s. 57(2) of the Contracts Act. The section states:
Contract to do act afterwards becoming impossible or
unlawful.
(2) A contract to do an act which, after the contract
is made, becomes impossible, or by reason of some event which the promisor
could not prevent, unlawful, becomes void when the act becomes impossible
or unlawful.
[30] In the present case, there is no evidence
that it had become impossible or that there was impracticability to complete
the Sang Suria Condominium. On the contrary, the undisputed fact is that the
Sang Suria Condominium project was eventually completed in September 2002,
albeit after a very long delay. Hence, the question of frustration does not
arise.
[31] In any case, in order to successfully invoke
the doctrine of frustration, it is not sufficient for the defendant to
merely refer to the national economic crisis of 1997-1998 and the
consequential dire financial position of its parent company, YTL Land and
Development Berhad (see paras. 8 and 9 of the defendant's affidavit at encl.
5). More needs to be established. There had to be a radical change in
circumstances. The circumstances under which the doctrine may be invoked
have been clearly explained by Lord Denning MR in the English Court of
Appeal case of The Eugenia [1964] 2 QB 226. In this case cited, the
Suez Canal was blocked and a vessel had to go round by the Cape. The
question arose whether the charterparty was frustrated. Lord Denning said:
This means that once again we have had to consider the
authorities on this vexed topic of frustration. But I think the position
is now clear. It is simply this: if it should happen, in the course of
carrying out a contract, that a fundamentally different situation arises
for which the parties made no provision - so much so that it would not be
just in the new situation to hold them bound to its terms - then the
contract is at an end.
It was originally said that the doctrine of frustration
was based on an implied term. In short, the parties, if they had foreseen
the new situation, would have said to one another: "If that happens, of
course, it is all over between us". But the theory of an implied term has
now been discarded by everyone, or nearly everyone, for the simple reason
that it does not represent the truth. The parties would not have said: "It
is all over between us". They would have differed about what was to
happen. Each would have sought to insert reservations or qualifications of
one kind or another. Take this very case. The parties realized that the
canal might become impassable. They tried to agree on a clause to provide
for the contingency. But they failed to agree. So there is no room for an
implied term.
...
We are thus left with the simple test that a situation
must arise which renders performance of the contract "a thing radically
different from that which was undertaken by the contract", see Davis
Contractors Ltd v. Fareham Urban District Council by Lord Radcliffe.
To see if the doctrine applies, you have first to construe the contract
and see whether the parties have themselves provided for the situation
that has arisen. If they have provided for it, the contract must govern.
There is no frustration. If they have not provided for it, then you have
to compare the new situation with the situation for which they provide.
Then you must see how different it is. The fact that it has become more
onerous or more expensive for one party than he thought is not sufficient
to bring about a frustration. It must be more than merely more onerous or
more expensive. It must be positively unjust to hold the parties bound. It
is often difficult to draw the line. But it must be done. And it is for
the courts to do it as a matter of law.
[32] Although I am prepared to take judicial
notice of the national economic crisis of 1997-1998 and to accept that there
was evidence of consequential financial hardship suffered by the defendant,
nevertheless, I am not inclined to hold that, by reason of this economic
crisis and the consequential financial hardship, a fundamentally different
situation had arisen that rendered it impossible or impractical for the
defendant to complete the condominium project, or to complete it with
reasonable delay. As I have said in Tai Kim Yew v. Sentul Raya Sdn. Bhd.
[2004] 3 CLJ 310, every businessman knows that there is a risk in any
commercial venture that he undertakes and that economic conditions, be it
international or national, is never static but always fluctuates; and he
must be prepared for any eventuality, whether favourable or adverse to him.
Therefore justice demands that he should not be allowed to use such an
adverse eventuality as an excuse to evade performance of the contract. And
it is worth repeating the following judicial policy as enunciated by Lord
Denning in the case just cited:
The fact that it has become more onerous or more
expensive for one party than he thought is not sufficient to bring about a
frustration. It must be more than merely more onerous or more expensive.
[Order in terms in respect of prayers 1(a) and (b) with
costs, but with a set off of RM877.36; costs to be taxed in accordance with
the Subordinate Courts Rules 1980;] |