TAN SRI G DARSHAN SINGH V. LOKE KEE DEVELOPMENT SDN BHD & ANOR
HIGH COURT MALAYA, KUALA LUMPUR
[CIVIL SUIT NO: S6-22-1040-2007]
MOHD YAZID MUSTAFA JC
10 OCTOBER 2008
JUDGMENT
Mohd Yazid Mustafa JC:
Introduction
[1] I had, on 23 June 2008, dismissed both encls. 27 and 24 ie, the
plaintiff's appeal against the decision of the senior assistant registrar
in allowing the 2nd defendant's striking out application in encl. 21 and
the 1st defendant's appeal against the decision of the senior assistant
registrar's in allowing the plaintiff's summary judgment application in
encl. 9.
[2] The plaintiff's summary judgment application in encl. 9 against the
1st and 2nd defendant is for liquidated ascertained damages for late
delivery of vacant possession of a condominium unit amounting to
RM334,691.64, interest at the rate of 10% per annum on RM334,691.64 from
10 September 2007 until full settlement and costs.
[3] The 2nd defendant is applying through encl. 21 under O. 18 r. 19 RHC
1980 to strike out the plaintiff's claim.
Summary Of Facts
[4] On 7 September 1995, the plaintiff and the 1st defendant entered into
a sale and purchase agreement (the sale and purchase agreement) for the
sale and purchase of a unit at Sri Emas Condominium (the condominium unit)
for the purchase price of RM314,010 (the purchase price). Time was of the
essence of the contract as stipulated in cl. 7 of the sale and purchase
agreement. (Exhibit DSG1 encl. 9)
[5] It is also a term of the sale and purchase agreement that 'vendor' ie,
the 1st defendant also includes its successors in title and permitted
assigns (Ibid at cl. 31(h)) and that the sale and purchase agreement would
be binding on the successors in title and permitted assigns of the 1st
defendant, the heirs, personal representatives, successors in title and
permitted assigns of the plaintiff. (Ibid at cl. 32)
[6] Vacant possession of the property and completion of common facilities
were to be given to the plaintiff 36 months from the date of the agreement
as stipulated by cl. 22(1) and cl. 24(1) of the sale and purchase
agreement, ibid ie, on 7 September 1998. The said date came and vacant
possession was not handed to the plaintiff.
[7] Clause 22(2) and cl. 24(2) of the sale and purchase agreement
stipulate that failure to deliver vacant possession complete with common
facilities will result in the 1st defendant's liability to pay liquidated
ascertained damages to the plaintiff. Clause 22(2) of the sale and
purchase agreement stipulates that liquidated ascertained damages for late
delivery of vacant possession are to be calculated at the rate of 10% per
annum on the purchase price on a day to day basis. Ibid
[8] On 15 September 2005, the 1st defendant executed a 'white knight'
agreement with the 2nd defendant (the white knight agreement). (Exhibit
DSG3 encl. 9).The 2nd defendant's role was to revive the abandoned
condominium project (Ibid at cl. 2(a)) and to procure the purchasers'
(including the plaintiff's) agreement to waive their rights to liquidated
ascertained damages. (Ibid at cl. 2(e)). Clause 2(e) of the white knight
agreement was inserted notwithstanding preamble (g) where it is clearly
stated that the 1st defendant would continue to be liable for liquidated
ascertained damages for its failure to deliver vacant possession within 36
months from the date of the sale and purchase agreement.
The 1st Defendant's Contention
[9] The 1st defendant argue that the reason vacant possession could not be
delivered within the stipulated time and the fact for the appointment of
the 2nd defendant is attributed to the Asian financial and economic crisis
in the late 1990s that inadvertently affected the financial standing of
the 1st defendant. The 1st defendant is not denying that they were late in
delivering vacant possession or that the plaintiff has never, at all
material times, waived his right to liquidated ascertained damages. The
1st defendant's argument is that the Asian financial crisis is a triable
issue for the court to consider because granting summary judgment would
defeat the practice amongst the construction industry in appointing 'white
knights' to revive abandoned housing projects. The fact that the plaintiff
had never complained about the continuation of the said project by the 2nd
defendant amounts to acquiescence. The plaintiff cannot now claim for
liquidated ascertained damages when his unit has been completed and
delivered to him.
The 2nd Defendant's Contention
[10] The 2nd defendant's argument in applying for the striking out of the
plaintiff's claim against them is that the 2nd defendant is not
financially liable towards the plaintiff for any late delivery of vacant
possession. The 2nd defendant's role is merely to revive the condominium
project which they have duly done in accordance to the 'white knight'
agreement with the 1st defendant.
The Plaintiff's Argument
[11] The plaintiff's argument is that at all material times, he has never
agreed to waive his right to claim for LAD for late delivery of vacant
possession of his condominium unit. The plaintiff contends further that he
has never agreed to the appointment of the 2nd defendant to complete his
unit. Therefore, the 1st defendant is liable to pay LAD. The 2nd defendant
has agreed with the 1st defendant to be responsible towards the plaintiff
by virtue of cl. 3 of the 'white knight' agreement. (Exhibit DSG3 encl.
8). If it were otherwise, the said cl. 3 would not have been inserted.
The Law
[12] The 1st defendant is a housing developer and the property in question
is a condominium unit. The relevant statutory provision regulating and
controlling the activity of the 1st defendant is reg. 11(1) of the Housing
Developers (Control and Licensing) Regulations 1989 enacted pursuant to
the Minister's powers under s. 24 of the Housing Developers (Control and
Licensing) Act 1966. For ease of reference, reg. 11(1) is reproduced
below:
Every contract of sale for the sale and purchase of a housing
accommodation together with the subdivisional portion of land appurtenant
thereto shall be in the form prescribed in Schedule G and where the
contract of sale is for the sale and purchase of a housing accommodation
in a subdivided building, it shall be in the form prescribed in >Schedule
H.
[13] Clause 22(1) and cl. 22(2) of the sale and purchase agreement are
reproductions of the relevant provisions under Schedule H of the Housing
Developers (Control and Licensing) Act 1966. Regulation 11(3) provides for
an exception to the housing developers duty that stipulates that:
Where the Controller is satisfied that owing to special circumstances or
hardship or necessity compliance with any of the provisions in the
contract of sale is impracticable or unnecessary, he may, by a certificate
in writing, waive or modify such provisions:
Provided that no such waiver or modification shall be approved if such
application is made after the expiry of the time stipulated for the
handing over of vacant possession under the contract of sale or after the
validity of any extension of time, if any, granted by the Controller.
Finding
[14] From a reading of reg. 11(1) and (3), it is clear that for the 1st
defendant to exempt itself from its statutory obligations towards the
plaintiff viz. to be exempted from paying liquidated ascertained damages
for late delivery of vacant possession of the property, the 1st defendant
would need to obtain the controller's written consent for exemption and
the application has to be made before the 36 months had expired. In the
present suit, the 1st defendant has not forwarded any such evidence to
justify its stand that it is not liable for liquidated ascertained
damages.
[15] I find that the plaintiff has never waived his rights to claim for
liquidated ascertained damages for late delivery of vacant possession of
his condominium unit. The 1st defendant is not merely morally responsible
to complete the condominium project including the plaintiff's unit. The
1st defendant has a contractual duty to perform under cl. 22 and cl. 24 of
the sale and purchase agreement that stems from a statute viz. The Housing
Developers (Control and Licensing) Act 1966.
[16] The fact that the 1st defendant was financially affected by the Asian
financial crisis thus unable to complete the condominium project on time
does not detract from this statutory contractual duty. Here, I would pause
to refer to the recent decision of the Court of Appeal in Sentul Raya Sdn
Bhd v. Hariram Jayaram & Ors. and Other Appeals [2008] 4 CLJ 618 at 626
para. [8] where His Lordship Gopal Sri Ram JCA held "In our opinion there
is no merit in the appellant's argument. So far as s. 56(3) of the
Contracts Act 1950 is concerned, it deals with contracts generally. The
contract which has fallen for construction in the present cases is a
special contract. It is prescribed and regulated by statute. While parties
in normal cases of contract have freedom to make provisions between
themselves, a housing developer does not enjoy such freedom. Hence,
parties to a contract in Form H cannot contract out of the scheduled form.
Terms more onerous to a purchaser may not be imposed. So too, terms
imposing additional obligations on the part of a purchaser may not be
included in the statutory form of contract. It follows that the
requirement of notice under s. 56(3) which is an additional obligation to
the detriment of the purchaser cannot be imposed on the respondents here
in the light of the statutory scheme under the Act. This is evident in the
language of cl. 22(2). On its proper construction, the clause makes a
housing developer immediately liable to a purchaser in liquidated damages
once the date for completion passes. Put differently, cl. 22(2) excludes
the operation of s. 56(3). This is another reason for holding that s.
56(3) of the Contracts Act 1950 does not apply in cases falling under the
Act."
[17] It is an undisputed fact that the plaintiff has paid the purchase
price. Under the sale and purchase agreement and even under general
contract law, the plaintiff is contractually entitled to receive
consideration ie, the delivery of his condominium unit. The sale and
purchase agreement goes further to provide the plaintiff, as a purchaser,
protection against the eventuality that vacant possession of the unit is
delivered late in the form of liquidated ascertained damages.
[18] The sale and purchase agreement does not exempt the 1st defendant
from paying liquidated ascertained damages because of any financial
problems. I would once again refer to the above decision of the Court of
Appeal at p. 628 para. [13] "Applying the foregoing test, we are of the
view that the defence of frustration is not available to the appellant.
The 1997 financial crisis merely made it more onerous or perhaps more
expensive for the appellant to perform its obligations. It did not render
the contract radically different. There is a further reason why the plea
of frustration should fail. Under reg. 11(3) of the Regulations it was
open for the appellant to make representations to the Controller of
Housing - to quote from the Regulation - "owing to special circumstances
or hardship or necessity compliance with any of the provisions in the
contract of sale is impracticable or unnecessary." In our judgment reg.
11(3) clearly excludes the operation of the doctrine of frustration in
respect of contracts regulated by the Act."
[19] The fact that there was a 3rd party ie, the 2nd defendant being
appointed to revive the abandoned condominium project also does not exempt
the 1st defendant from liability to pay liquidated ascertained damages.
[20] It is pertinent to note that the 1st defendant had imposed an
additional condition which is onerous on the purchasers to which the
plaintiff had refused to acquiesce ie, that liquidated ascertained damages
be waived before the abandoned condominium project was to be revived by
the 2nd defendant. The plaintiff's refusal to agree to this onerous
condition also does not release the 1st defendant from its statutory
contractual duty to pay liquidated ascertained damages. The reason is the
operation of cl. 22(2) of the sale and purchase agreement.
[21] Therefore, I find that there are no triable issues between the
plaintiff and the 1st defendant. The plaintiff is entitled to claim for
liquidated ascertained damages.
[22] The 2nd defendant was appointed to revive the abandoned condominium
project and not to replace the 1st defendant as the 'vendor' in the sale
and purchase agreement between the plaintiff and the 1st defendant. It is
clear that cl. 3 of the 'white knight' agreement states that the 2nd
defendant is under no obligation to complete any units to which the
purchaser has not agreed to appoint the 2nd defendant as the 'white
knight'.
[23] The plaintiff has clearly denied his agreement to appoint the 2nd
defendant to complete his unit. However, it is practically impossible for
the 2nd defendant to complete the condominium project without also
completing the plaintiff's unit. To do otherwise is impractical.
Furthermore, Preamble g of the 'white knight' agreement clearly stipulates
that it is the 1st defendant which is liable to pay LAD for late delivery
of vacant possession and not the 2nd defendant. Therefore, the 2nd
defendant is not liable towards the plaintiff.
[24] Based on the above reasons, I had:
(i) dismissed the 1st defendant's appeal in encl. 24 and upheld the
summary judgment against the 1st defendant for RM334,691.64; interest at
the rate of 8% per annum on RM334,691.64 from the date of judgment until
full settlement with costs; and
(ii) dismissed the plaintiff's appeal in encl. 27 and upheld the order to
have the writ and statement of claim against the 2nd defendant struck out
with costs.
|