Penang
Development Corporation
- vs -
Khaw
HIGH COURT OF MALAYA
Coram
MOHAMED DZAIDDIN J
14 JANUARY 1993
Judgment
Mohamed Dzaiddin J
This is an appeal from the decision of the magistrate in Georgetown given on
20 January 1987 who held that the plaintiffs had established a reasonable
cause of action against the defendant in their amended statement of claim.
The plaintiffs’ claim in the action is for damages for late delivery of
vacant possession of a unit of flat known as Flat No 17.6, Macallum Street
Ghaut Slab Block GT7 (‘the said flat’) which they purchased from the
defendant for RM62,000. The parties executed a sale and purchase agreement
on 25 October 1982. It is common ground that the said agreement was silent
regarding the date of delivery of vacant possession. Nonetheless, the
delivery of vacant possession of the said flat was finally made by the
defendant to the plaintiffs on 22 January 1986 which was more than three and
a half years after the execution of the sale and purchase agreement.
By their amended statement of claim, the plaintiffs averred in para 4 that
vacant possession of the said flat must be delivered within a reasonable
time. In this context, the plaintiffs relied on the 24 months’ period under
the Housing Developers (Control and Licensing) Regulations 1982 (‘the
Regulations’) as a reference to determine the issue of reasonable time.
Hence, by para 5, the plaintiffs alleged that, in consequence of the
averment in para 4, the defendant had failed to deliver vacant possession
within a reasonable time which was 455 days exceeding the reasonable time
period of 24 months. In the premises, they claimed to have suffered loss and
damage.
The defence of the defendant was that the amended statement of claim
disclosed no cause of action and the plaintiff’s action be dismissed with
costs.
In the appeal before me, the same point was taken up by Mr. Lim Ewe Hock,
aside from two other grounds as stated in the memorandum of appeal. So, the
crucial issue in this appeal is quite simple and straightforward, which is,
whether the amended statement of claim discloses a reasonable cause of
action.
A reasonable cause of action means a cause of action with some chance of
success when only the allegations in the pleadings are considered (per Lord
Pearson in Drummond-Jackson v British Medical Association [1970] 1 WLR 688).
Here, para 4 merely averred that the delivery must be made within a
reasonable time which was to be determined by analogy to the Regulations.
Paragraph 5 further alleged that the defendant had failed to deliver vacant
possession within a reasonable time. Thus, have the two paragraphs of the
amended statement of claim disclosed a reasonable cause of action to enable
the plaintiffs to succeed in their claim for damages? In my judgment, there
is none.
First, it is common ground that the written agreement did not fix any time
for the performance of the contract. So when no time is specified, the
contract must be performed within a reasonable time - s 47 Contracts Act
1950. What is ‘a reasonable time’ is, in each particular case, a question of
fact (ibid). However, the plaintiffs cannot arbitrarily fix the time. It
must be reasonable having regard to the state of things at the time when
notice was given. In Stickney v Keeble [1915] AC 386, the English House of
Lords held as follows:
Where in a contract for the sale of land the time fixed for completion is
not made of the essence of the contract, but the vendor has been guilty of
unnecessary delay, the purchaser may serve upon the vendor a notice limiting
a time at the expiration of which he will treat the contract as at an end,
and in determining the reasonableness of the time so limited the court will
consider not merely what remains to be done at the date of the notice, but
all the circumstances of the case, including the previous delay of the
vendor and the attitude of the purchaser in relation thereto.
Secondly and more importantly, the amended statement of claim has failed to
plead that the plaintiffs have given notice to the defendant to complete the
delivery of vacant possession within a reasonable time. What had been
pleaded was merely an allegation that the defendant had failed to deliver
vacant possession within reasonable time (para 5). In my opinion, a written
notice giving time to complete the delivery is necessary since time by which
the contract was to be completed has not been stipulated, nor made the
essence of the contract. According to 9 Halsbury’s Law of England (4th Ed)
para 485:
In cases where time is not originally of the essence of the contract, or
where a stipulation making time of the essence has been waived, time may be
made of the essence, where there is unreasonable delay, by a notice from the
party who is not in default fixing a reasonable time for performance and
stating that, in the event of non-performance within the time so fixed, he
intends to treat the contract as broken. The time so fixed must be
reasonable having regard to the state of things at the time when the notice
is given, and to all the circumstances of the case.
In Green v Sevin (1879) 13 Ch D 589, Fry J stated at p 599:
One of the earliest cases on this doctrine of engrafting time by notice is
Taylor v Brown 2 Beav 180 , and there Lord Langdale, the then Master of the
Rolls, expressed his view in this way: ‘Where the contract and the
circumstances are such that time is not in this court considered to be of
the essence of the contract - in such case, if any unnecessary delay is
created by one party, the other has a right to limit a reasonable time
within which the contract shall be perfected by the other.’ So in King v
Wilson 6 Beav 124, the same Master of the Rolls laid down the principle in
these words: ‘Though time may not be of the essence of a contract, yet where
there is great and improper delay on one side, the other party has a right
to fix a reasonable time within which the contract is to be completed.’ So
again, in Pegg v Wisden 16 Beav 239, Sir John Romilly said: ‘I concur also
in the decisions, that where time is not originally of the essence of the
contract, it may, in the case of improper delay, be made so by notice.’
Mr. BC Lim, counsel for the respondent, submitted that failure to issue a
notice fixing a reasonable time was not fatal. He relied on Raineri v Miles
[1980] 2 All ER 145 and Quah Ban Poh v Dragon Garden Pte Ltd [1985] 2 MLJ
159. After examining both decisions, I find they do not support the
respondent’s case. One of the issues in Raineri 4 was the effect of service
of completion notice calling on the appellants to complete their contract of
sale, and in Quah Ban Poh, it was held, inter alia, that if the defendant
had wanted to make time again of the essence of the contract, it should have
given the plaintiff a notice fixing a reasonable time within which he must
pay the last instalment.
Therefore, for the reason that the amended statement of claim has failed to
plead the vital issue of notice fixing a reasonable time, it is my
conclusion that the amended statement of claim has not disclosed a
reasonable cause of action.
Thirdly, the learned magistrate was wrong in law to accept the provision of
r 12(1) of the Regulations as a ‘reference to determine the question of
reasonable time’. I am satisfied that the defendant, being an exempt body
under s 2 of the Housing Developers (Control and Licensing) Act 1966 (Rev
1973), the provisions of cl 18(1) of Sch E of the Regulations do not apply
to them.
For the above reasons, this appeal is allowed with costs.
Cases
Drummond-Jackson v British Medical Association [1970] 1 WLR 688; Stickney v
Keeble [1915] AC 386; Green v Sevin (1879) 13 Ch D 589; Raineri v Miles
[1980] 2 All ER 145; Quah Ban Poh v Dragon Garden Pte Ltd [1985] 2 MLJ 159
Legislations
Contracts Act 1950: s.47
Authors and other references
9 Halsbury’s Law of England (4th Ed)
Representations
EH Lim (Lim Kean Chye) for the appellant.
BC Lim (Lim Boo Chang & Co) for the respondents.
Notes:-
This decision is also being reported at [1993] 2 MLJ 161.
|