CHIN SIN MOTOR WORKS SDN. BHD. & ANOR.
V. AROSA DVPT. SDN. BHD. & ANOR.
HIGH COURT MALAYA, KUALA LUMPUR
LIM BENG CHOON J
[CIVIL SUIT NO. S7-22-536-90]
16 OCTOBER 1991
JUDGMENT
Lim Beng Choon J:
In this action the 1st plaintiff purchased a piece of land from the 1st
defendant who also agreed to construct a building thereon for the purchase
price of RM460,000. The first plaintiff entered into a loan agreement with
the 2nd plaintiff who was to make progressive payments towards the purchase
price. After filing their writ and statement of claim the plaintiffs applied
under O. 14 r. 1 of the Rules of High Court 1980 for leave to enter
interlocutory judgment against both the 1st defendant and the 2nd defendant
who was the architect of the 1st defendant in respect of the construction of
the building. The application for summary interlocutory judgment of the
plaintiff was dismissed by the Senior Assistant Registrar (SAR) on 30 March
1991. Being dissatisfied with the decision of the SAR the plaintiffs
appealed to me on 1 April 1991. At the hearing before me on 25 July 1991
Counsel for the plaintiffs confined his submission against the decision of
the SAR in respect of the 2nd defendant and abandoned the decision of the
SAR against the 1st defendant. I allowed the appeal against the 2nd
defendant and directed that damages against the 2nd defendant be assessed by
the Court. The 2nd defendant now appeals against my decision to the Supreme
Court and I hereby give my grounds of judgment. It is necessary at the
outset to give a brief summary of the averments of the plaintiffs as
appeared in their statement of claim. By a written sale and purchase
agreement dated 1 April 1985 made between the 1st plaintiff and the 1st
defendant, (the sale and purchase agreement) the 1st defendant agreed to
sell and the 1st plaintiff agreed to purchase a piece of land with a
building to be erected thereon by the 1st defendant. By Clause 4(1) of the
said agreement the purchase price was to be paid to the 1st defendant by
instalments progressively according to the stages of completion of the
building set out in the 3rd Schedule of the said agreement. By item (3) of
the 3rd Schedule, an instalment in the sum of RM69,000 would become due and
payable to the 1st defendant on handing over vacant possession of the land
and building with connection of water and electricity supply to the said
building. By item (4) of the 3rd Schedule a final instalment of RM23,000
would be due and payable to the first defendant but which was to be held by
the 1st defendant's solicitors as stakeholders and payments thereof to be
made in two instalments that is to say a sum of RM11,500 upon the expiry of
6 months and the balance of RM11,500 at the expiry of 12 months after
handing over of vacant possession. At all material times the 2nd defendant
was the architect for the 1st defendant and as such it was the 2nd
defendant's duty under the sale and purchase agreement to certify each stage
of completion of the building for which certification would be relied upon
by the 1st plaintiff and/or its financier the 2nd plaintiff for the purposes
of making instalment payments to the 1st defendant of the purchase price.
The 2nd defendant therefore owed a duty to the 1st plaintiff to ensure that
its certification of each stage of completion of the building would be true
and accurate. On 22 December 1986, the 2nd defendant certified in writing
that the building had been completed to the stage of handing over of vacant
possession and connection of water and electricity supply to the building.
By a letter dated 24 December 1986, the 1st defendant submitted to the 2nd
plaintiff the certificate of the 2nd defendant notifying the 2nd plaintiff
that the sums of RM69,000 and RM23,000 had become due and payable by the 1st
plaintiff to the 1st defendant and its solicitors respectively. On 13
January 1987 in reliance on the 1st defendant's letter and the 2nd
defendant's certificate, the 2nd plaintiff on behalf of the 1st plaintiff,
paid to the 1st defendant and its solicitors the said sums of RM69,000 and
RM23,000 respectively. It was asserted that in fact electricity supply was
connected to the building thereby enabling the 1st defendant to deliver
vacant possession of the building to the 1st plaintiff only on 7 March 1990
and the certification of the 2nd defendant and the notification of the 1st
defendant was false and misleading. The 1st defendant had therefore received
the said sums of RM69,000 and RM23,000 to the use of the 1st plaintiff over
the period of 13 January 1987 to 7 March 1990. The 2nd defendant was
negligent in the certification and the plaintiffs gave particulars of the
2nd defendant's negligence which were:
(1) Certifying that the abovementioned stage of completion had been
reached when it was not true;
(2) Failure to ascertain the actual stage of completion; and
(3) Knew or ought to have known that the 1st plaintiff and/or its
financiers would rely upon the certification to make instalment payments
to the 1st defendant when it was not due and payable.
By reason of the matters aforesaid, the 1st plaintiff therefore claimed
against both the 1st and 2nd defendant:
(a) damages referred to in para. 15 of the statement of claim;
(b) interest thereon at such rate and period as the Court deemed fit;
(c) costs.
It is to be noted that I only summarised the averments of the plaintiffs'
statement of claim insofar as they are related to the claim of the
plaintiffs against the 2nd defendant. I have omitted most of the averments
of the plaintiffs relating to their claim against the 1st defendant since at
the hearing of the plaintiffs' appeal Counsel for the plaintiff had as
stated earlier confined himself in attacking the decision of the SAR insofar
as it concerned the 2nd defendant. In its defence, the 2nd defendant denied
all the charges of negligence made against it and particularly averred that
firstly the 2nd defendant did not owe a duty of care to the plaintiffs.
Secondly in any event at the time of issuing of its certificate of payment
all the connections for the supply of electricity and water were completed.
It was through the 1st plaintiff's unwillingness and/or negligence in
failing to pay the necessary deposits to the authorities concerned that they
would not supply electricity and water to the building. The 2nd defendant
also denied that the 1st plaintiff suffered any losses or damages and put
the 1st plaintiff to strict proof of the same. In its affidavit in support
of its application for summary interlocutory judgment the director Low Hup
Seng of the 1st plaintiff affirmed the said affidavit on 4 October 1990 in
which the following relevant documents were annexed thereto as:
Exhibit "LHS1": the sale and purchase agreement executed between the
1st defendant and the 1st plaintiff on 15 April 1985.
Exhibit "LHS2": the certification of the 2nd defendant dated 22
December 1986 in which it was stated:
This is to certify that the 3½ storey shophouse on Lot Nos. SH-1 to
SH-24 Taman Putra Sulaiman-1B have been completed up to the stage of:
Handing over of vacant possession and connection of water and electricity
supply to the building...15%. To be held by vendor's solicitors as
stakeholders ... 5%
Signed
Wong Kin Men Associates,
Chartered Architects
Room 4.107-4.109
4th Floor Wisma Central
Jalan Ampang 50450 Kuala Lumpur
Exhibit "LHS3": the first defendant's notice to the 2nd plaintiff dated
24 December 1986 forwarding the 2nd defendant's certificate of payment of:
(i) Handing over of vacant possession & connection of water &
electricity supply of the building 15% RM69,000
(ii) To stakeholders:
M/s Syed Alwi
Ng & Teoh 5% RM23,000
RM92,000
Exhibit "LHS6": letter from the 1st plaintiff's solicitors to the 2nd
defendant dated 26 May 1990 which contained the following passages:
3. We are instructed that the said certification was a
misrepresentation and erroneous as the electricity supply was connected to
our client's property which is Lot SH19 only on 7 March 1990.
4. By reason of the above our client has been caused to pay unnecessary
interest amounting to RM30,901.28 for the loan of the above said sums of
RM69,000 and RM23,000 over the period of 13 January 1990 1987 (sic) to 7
March 1990.
5. Our further instructions are to demand from you which we hereby do
that you compensate our client for the incurrence of the interest
aforesaid. Take notice that unless the said sum of RM30,901.28 and a
further sum of RM150 being our solicitors' cost for this letter is paid to
us as solicitors within 7 days from the date hereof our instructions are
to commence legal proceedings against you for the recovery thereof and
further interest and costs.
In the affidavit, it was stated that:
the defendants are and were justly and truly liable to the 1st
plaintiff for the damages together thereon. As a result of certain
payments made to the 1st defendant pursuant to a certificate issued by the
2nd defendant
... there is no defence to this action except for the amount of damages
as regards the 1st plaintiff's claim for damages against both defendants.
Another affidavit was affirmed by Low Hup Seng on behalf of the 1st
plaintiff on 8 November 1990 (Encl. 9) in which it was stated:
3. As further evidence that electricity supply was not connected right
up to at least 16 December 1989 (if not later) now produced and shown to
me marked accordingly are copies of the following documents:
3.1 "LHS7" : letter dated the 18 October 1989 from Biro Pengaduan Awam,
Jabatan Perdana Menteri;
3.2 "LHS8" : letter dated the 15 November 1989 from the 1st defendant
enclosing LLN forms for completion before electricity supply would be
connected;
3.3 "LHS9" : letter dated the 16 November 1989 from the 1st plaintiff
to the 1st defendant (returning the LLN forms duly signed and chopped with
a reminder that electricity deposit of RM1,180 had been posted to the 1st
defendant on 14 November 1989).
4. As pleaded in para. 12 of the statement of claim, vacant possession
was delivered by the 1st defendant to me on 7 March 1990. Now produced and
shown to me marked "LHS10" is a true copy of a letter dated 14 February
1990 from the 1st defendant to the 1st plaintiff requesting the 1st
plaintiff to take delivery of vacant possession. Now produced and shown to
me marked "LHS11" is a true copy of the document dated 7 March 1990. I
signed acknowledging receipt of the keys to the house and of taking
possession" (words in parenthesis supplied).
The 1st defendant through its chairman Lin Kim Hock affirmed an
affidavit-in-reply dated 13 December 1990 in which it was stated inter
alia that as the 1st defendant had obtained an order in Civil Suit
D1-24-281-84 approving a composite scheme of arrangement proposed to be made
between "the applicants (which included the 1st defendant, their creditors
and the holders of the scheme shares") the plaintiffs could not now proceed
with their action against the 1st defendant.
The 2nd defendant through its chairman, Wong Kin Men, affirmed an
affidavit dated 19 December 1990 (Encl. 12) in which it was stated firstly
that pursuant to Clauses 15(1) and (2) of the sale and purchase agreement it
was the responsibility of the 1st defendant as vendor to cause to be laid
all necessary water, electricity and sewerage mains to the building at its
own costs, and the 1st plaintiff as purchaser was liable to pay for the
deposits of installation of water and electricity meters. The delay in
handing over vacant possession of the land and building was not due to the
negligence of the 2nd defendant as it had duly checked and was satisfied
that the project was completed when it issued the certification on 18
December 1986. The 2nd defendant could not be asked to bear the burden of
ensuring the 1st defendant's responsibility of applying to the appropriate
authority for the electricity supply. From the documents produced by the 1st
plaintiff annexed to the affidavits of Low Hup Seng it clearly showed that
it was due to the failure on the part of the 1st defendant to deliver vacant
possession on time and not in any way due to the fault of the 2nd defendant.
In his submission, Counsel for the 2nd defendant submitted that the
pleadings of the plaintiffs created some confusion in particular para. 15 of
the statement of claim in which the plaintiffs averred that the 1st
plaintiff had suffered loss and damage and gave particulars of the said loss
and damage. According to Counsel the pleading in the said para. 15 was bad
because the 2nd defendant could not be expected to know the claim against
him and this would prejudice the 2nd defendant. It is to be noted that
Counsel had not said a single word regarding the question of liability on
the part of the 2nd defendant.
From the pleadings of the respective parties and the affidavit evidence
adduced, I have no doubt at all that the 2nd defendant is guilty of
negligence and/or misrepresentation and I say so for these reasons. There is
firstly no denial that the 2nd defendant certified final payments of two
sums of RM69,000 and RM23,000 on 22 December 1986. Under the Third Schedule
of the sale and purchase agreement item 3 and 4 payments for the two sums
were due only "On handing over of vacant possession and connection of
water and electricity". Pursuant to Clause 4(11) of the sale and
purchase agreement the balance of the purchase price would have to be paid
by instalments and at the time and in the manner as prescribed in the Third
Schedule thereto" and under subclause (2) of that clause it was stated:
Every notice referred to in the Third Schedule requesting for payment
shall be supported by a certificate under the hand of the vendor's
architect and every such certificate so signed
shall be proof of
the fact that the works therein referred to have been completed.
(Emphasis supplied)
Secondly there is equally no denial that the 2nd plaintiff, as financier
of the 1st plaintiff relying on the certification of the 2nd defendant made
payments of the said two sums to the 1st defendant on 13 February 1987.
Thirdly it is again indisputable that application for electricity supply
could only be made to LLN when the 1st defendant sent the relevant Forms to
the 1st plaintiff on 16 November 1989 and it was only on 14 February 1990
that the 1st defendant was ready to hand over vacant possession of the
building with water and electricity supply. Bearing in mind that had all the
electrical works been ready to receive electricity from the main supply of
LLN it would be a simple matter of filling some forms and payment of a
deposit whereupon LLN would take the necessary steps to supply electricity
to the building. The fact that an application for electricity could only be
made to LLN on or about 16 November 1989 must, on the balance of
probabilities, show that the electrical works had not been completed or
satisfactorily completed when the 2nd defendant issued its certificate on 22
December 1986. Had the electrical works been completed on the date of the
2nd defendant's certification, it is highly incredible that the 1st
defendant would have waited for nearly three years before requesting the 1st
plaintiff to apply to LLN for electricity supply. There is no earthly reason
for such a long delay had the electrical works been completed or
satisfactorily completed in 1986. The one and only conclusion that I can
arrive at is that the electrical works were not completed or satisfactorily
completed in 1986 when the 2nd defendant issued its certification on 22
December 1986. I reiterate that the 2nd defendant is guilty of negligence
and/or misrepresentation which caused the 1st plaintiff to suffer loss or
damage in that it had to pay interests to the 2nd plaintiff for the
premature release of the said two sums of money. Notwithstanding the above
finding it is still necessary to consider whether the 2nd defendant owed the
plaintiffs a duty of care for "no case of actionable negligence will arise
unless the duty to be careful exists (per Lord Wright in Grant v.
Australian Knitting Mills Ltd. [1936] AC 85 @ 103). The recognition of
liability for careless misstatements is settled by the House of Lords in
Hedley Byrne & Co. Ltd. v. Heller & Partners Ltd. [1964] AC 465. The
principle is that there is a duty situation whenever:
the party seeking information or advice was trusting the order to
exercise such a degree of care as the circumstances required, where it was
reasonable for him to do that and where the other gave the information or
advice when he knew or ought to have known that the inquirer was relying
on him.
This principle is advanced further in Dutton v. Bognor Regis Urban
District Council [1972] 1 QB 373. There a builder, X, had started to
build a house on land belonging to him and on the site of an old rubbish
tip, which had been filled in. The foundations were not strong enough to
support the kind of house that was being built on such insecure soil. An
inspector of the defendant Council negligently failed to discover that the
foundations were inadequate and in consequence approval was given to X to
proceed with the house. X did so and eventually sold the house to a
purchaser, who later sold it to the plaintiff. Serious structural defects
soon began to appear as the house subsided. The plaintiff sued the
defendants who were held liable. A point that emerges from this case is that
it is not even essential to show that the plaintiff relied on the
defendant's statement in buying the house. The liability of the defendant is
established once it is found that they owe a duty of care in giving the
approval to proceed with the building to the purchaser of the house.
Applying the principles laid down in the aforecited cases to the present
case, it is clear that the 2nd defendant whose duty was to issue a
certificate of final payments when the vacant possession of the house was
ready to be delivered complete with all electrical works to receive
electricity supply from LLN must surely owe a duty of care to the plaintiffs
when he knew or ought to have known that the plaintiffs would solely rely on
its certification to make payments to the 1st defendant. Finally as regards
to the pleadings in the statement of claim there is no doubt that the
plaintiffs were claiming against both the defendants for loss or damage
suffered by them due to the premature payments which caused them to have to
pay extra interest to their financier the 2nd defendant in the sum of
RM30,901.28 for the period from 13 January 1987 to 7 March 1990. This claim
was clearly pleaded in paras. 14 and 15 of the statement of claim. On the
grounds as stated above, I therefore allowed the appeal of the 1st plaintiff
against the 2nd defendant and directed that damages be assessed by the
Court.
|