This website is
 sponsored.gif

banner.gif

 Welcome    Main    Forum    FAQ    Useful Links    Sample Letters   Tribunal  

 

Stalled projects
25/10/2005 The Star Articles of Law with Bhag Singh

Matters relating to purchase of property continue to be of concern to the public whether they are citizens or not. This is because anyone can buy property in Malaysia though in the case of non-citizens there could be some restrictions.

Quite apart from the fact that there may be defects, one of the more frequent grievances of a house buyer is that of delay. It could be a delay in which completion is foreseeable, but sometimes there is likelihood that the project will be stalled indefinitely.

One option is for the house buyer to wait until the house is completed and then sue the developer for late delivery which is already allowable in all housing Sale and Purchase Agreements (SPA).

In fact the law prescribes a percentage of the cost of the residential properties to be paid as liquidated damages in case of delays by the housing developer.

However, a question that arises is whether a person who is a party to an SPA can in view of the fact that he is entitled to liquidated damages actually terminate the agreement if the house is not completed on time?

This question arises because it has at times been said that since a house buyer has already contractually agreed to be paid liquidated damages, he cannot therefore terminate the SPA and sue for damages.

The answer is that even though there is a clause conferring on the house buyer a right to liquidated damages for the period of the delay, the house buyer still has an option to terminate the agreement. The house buyer would, in such a case, also be entitled to claim damages.

The reason for this is based both on logic and common sense. If such a clause precluded the house buyer from terminating the agreement, it would create a ridiculous situation. This would especially be so if there was an indefinite delay or abandonment of the project.

Ordinarily in such a scenario the house buyer could upon termination of the SPA be entitled to a refund of whatever he has paid. In addition to that, he would be entitled to damages. The measure of this would be the loss suffered by him.

In ordinary circumstances the loss would have to be determined by looking at the value of similar properties at the time the breach took place. Thus it would be the opportunity that is lost which would have been the difference between the purchase and the appreciated price.

However, where there is a liquidated damages claim in the SPA, the more appropriate measure would be the computation of the agreed liquidated damages for the period between when the house ought to have been completed and the point of time when the agreement was terminated.

If during this period the property price has appreciated steeply then the agreed liquidated damages may not measure up to the actual damage suffered.

However, if property prices have been stable during this period and there has been no appreciation or even a fall in prices then the liquidated damages would turn out to be a windfall.

Of course, it has been said in some cases that the house buyer should wait until the house is completed. However, this approach was disapproved of in Xavier Kan Yoon Mook vs Insun Development Sdn Bhd in which the court said this would cause hardship to the plaintiff for two potent reasons.

Firstly, if the house buyer is supposed to wait for the said house to be built and delivered to him before he can sue the defendant for liquidated damages, then at the end of the day the house buyer would be put in great jeopardy because the limitation period might set in.

Secondly, if the house buyer cannot sue the housing developer for liquidated damages upon its failure to comply with the agreement then it would be tantamount to the court allowing eternal procrastination with no possible and immediate form of remedy to the house buyer.

And the court went on to quote an earlier judgement the effect of which was that a party who rightly rescinds a contract is entitled to compensation for any damage which he has sustained.

It would therefore be the position in law that once the time set for completion has passed, the house buyer can terminate the agreement and seek a refund of whatever has been paid as well as damages which can be proved.

While on this point another reader, who is a foreigner, says he has been locked in litigation with a housing developer over liquidated damages which he is entitled to.

When he had a meeting with the developer to resolve the matter, he was told by one of the developer's officers that in some of the cases in court, the presiding officer had told the house buyer not to go all out because the developer was, after all, helping them get homes.

However, any such suggestion that is said to have been made in court must have been taken out of context. It cannot be said that in a transaction between a house buyer and a developer any one party is doing the other a unilateral favour.

It is a transaction in which there is a reciprocity of obligations and benefits. The housing developer gets the money which is committed by the house buyer. Similarly, the house buyer must get his house. Each must perform its obligation on time. If either causes a delay, the consequences are set out in the agreement.

Of course, the developer may face difficulties in terms of delays in getting the work done or supply of material on time and at prices he has anticipated. It is to get all these things done for which his reward is in his profits. If he fails to do so then he must honour his promises which, after all, he has voluntarily undertaken.

 

Main   Forum  FAQ  Useful Links  Sample Letters  Tribunal  

National House Buyers Association (HBA)

No, 31, Level 3, Jalan Barat, Off Jalan Imbi, 55100, Kuala Lumpur, Malaysia
Tel: 03-21422225 | 012-3345 676 Fax: 03-22601803 Email: info@hba.org.my

© 2001-2009, National House Buyers Association of Malaysia. All Rights Reserved.